Twitter | Search | |
vivaNext
vivaNext – designing and building a rapid transit system in York Region. Let us know your thoughts.
8,787
Tweets
772
Following
3,110
Followers
Tweets
vivaNext Sep 17
update: Temporary concrete barriers have been realigned and Hwy 7 westbound has reopened to 3 Lanes.
Reply Retweet Like
vivaNext Sep 17
this evening: temporarily closing the westbound lane closest to the concrete barriers on Highway 7 West at the ramp going to northbound Hwy400 to realign the concrete barrier that has been pushed towards the live lane
Reply Retweet Like
vivaNext Sep 17
Replying to @AbtinZohrabi @YRTViva
Hi Abtin, I'm looping in , which is in charge of service & operations (we're design-plan-build)
Reply Retweet Like
vivaNext Sep 15
update: Crews completed work ahead of schedule, so these entrances along are now open!
Reply Retweet Like
vivaNext Sep 14
More choices in how to travel brings more benefits, and there’s >> read our corporate newsletter
Reply Retweet Like
vivaNext Sep 14
: Crews reach another project milestone on ! Starting Monday, crews will begin installing paver stones, pouring concrete for the curb and paving the base-layer asphalt on the newly widened road. Details >>
Reply Retweet Like
vivaNext Sep 14
: Starting overnight Monday, crews will continue storm sewer installations at the southwest corner of and Richmond Heights. Details >>
Reply Retweet Like
vivaNext Sep 14
Hi , thanks for your feedback on the traffic; we know it's very busy. We're doing what we can to mitigate impacts, however there's significant construction in that area with multiple work operations happening. We're making progress. Appreciate your patience!
Reply Retweet Like
vivaNext Sep 14
Replying to @MichaelMay21
Hi Michael, ongoing work on northbound Atkinson vivastation. The southbound station construction to start after road widening, curb work, sewer work, base paving. If you're not yet subscribed to updates, you can do so at
Reply Retweet Like
vivaNext Sep 14
overnight work >> CIREAM paving on Highway7W, Bruce - Pine Valley , and Edgeley - Commerce. In addition, storm sewer work continues between Bruce & John Frank >> details
Reply Retweet Like
vivaNext Sep 14
To accommodate road widening on Centre from Hwy7 to Dufferin , traffic will be shifted to the north. Plus activating the traffic signals on Monday at Centre & ConcordRd/Wade Gate, and on Tuesday at Centre & VaughanBlvd/Carl Tennen >> details
Reply Retweet Like
vivaNext Sep 13
: As road widening activities progress, crews will continue curb installations and paving on , tomorrow and Monday. Details >>
Reply Retweet Like
vivaNext Sep 13
: The third temporary side street road closures along start tomorrow and include the entrances to Chapters/Pier 1 Imports/Starbucks [17440 Yonge] and Montana’s [17450 Yonge], and Newroads Subaru [17415 Yonge]. Details >>
Reply Retweet Like
vivaNext Sep 12
: To accommodate excavation for the future Weston Road vivastation, there will be overnight paving, line painting, a traffic shift & new traffic signals at the Hwy7-Weston intersection >> details
Reply Retweet Like
vivaNext Sep 12
>> ShopYonge and check out American Sound of Canada, GlamourGate Inc., and Manilla Halal Market.
Reply Retweet Like
vivaNext Sep 12
>> ShopYonge and check out A Plus Nails & Spa, and .
Reply Retweet Like
vivaNext Sep 11
: This summer, residents got a behind-the-scenes look at the bus rapidway construction project on during the Discover Your Yonge Walking Tours. via Details >>
Reply Retweet Like
vivaNext Sep 10
: Yongehurst Road at will be temporarily closed starting tomorrow as crews continue to install underground utilities. Details >>
Reply Retweet Like
vivaNext Sep 10
tonight’s paving to be rescheduled 🌧 ☔️ 🏊‍♂️
Reply Retweet Like
vivaNext Sep 8
update: Crews completed construction work ahead of schedule and we're pleased to advise that Millard Avenue West and Millard Avenue along are now open.
Reply Retweet Like