Cam Plant Hire Ltd 26 Jul 18
A 6 furlong gallop construction started this week Including excavation, drainage hardcore, geotextile membranes, and carpet finishing. 250M of excavation completed so far and 75M of drainage.145 Hyundai, 85 Kobelco, 55 komatsu & Dumpers on site! May the weather continue.😎👍🏼